Pennsylvania Department of Health
PARAMOUNT NURSING AND REHABILITATION AT FAYETTEVILLE, LLC
Building Inspection Results

Note: If you need to change the font size, click the "View" menu at the top of the page, place the mouse over the "Text Size" menu item, and select the desired font size.

Severity Designations

Click here for definitions Click here for definitions Click here for definitions Click here for definitions
Minimal Citation - No Harm Minimal Harm Actual Harm Serious Harm
PARAMOUNT NURSING AND REHABILITATION AT FAYETTEVILLE, LLC
Inspection Results For:

There are  45 surveys for this facility. Please select a date to view the survey results.

Surveys don't appear on this website until at least 41 days have elapsed since the exit date of the survey.
PARAMOUNT NURSING AND REHABILITATION AT FAYETTEVILLE, LLC - Inspection Results Scope of Citation
Number of Residents Affected
By Deficient Practice
Initial comments:Name: - Component: -- - Tag: 0000
Based on an Emergency Preparedness Survey completed on July 14, 2026, at Paramount Nursing and Rehabilitation at Fayetteville, Llc, it was determined there were no deficiencies identified with the requirements of 42 CFR 483.73.


 Plan of Correction:


Initial comments:Name: MAIN BUILDING - Component: 01 - Tag: 0000
Facility ID #420102

Component 01

Main Building

 

Based on a Medicare/Medicaid Recertification Survey completed on July 14, 2026, it was determined that Paramount Nursing and Rehabilitation at Fayetteville, Llc was not in compliance with the following requirements of the Life Safety Code for an existing health care occupancy. Compliance with the National Fire Protection Association's Life Safety Code is required by 42 CFR 483.90(a).

 

This is a one-story, Type II (000), unprotected noncombustible structure, without a basement, which is fully sprinklered.


 Plan of Correction:


NFPA 101 STANDARD Sprinkler System - Maintenance and Testing:This is a less serious (but not lowest level) deficiency and affects more than a limited number of residents, staff, or occurrences. This deficiency is one that results in minimal discomfort to the resident or has the potential (not yet realized) to negatively affect the resident's ability to achieve his/her highest functional status. This deficiency was not found to be throughout this facility.
Sprinkler System - Maintenance and Testing
Automatic sprinkler and standpipe systems are inspected, tested, and maintained in accordance with NFPA 25, Standard for the Inspection, Testing, and Maintaining of Water-based Fire Protection Systems. Records of system design, maintenance, inspection and testing are maintained in a secure location and readily available.
a) Date sprinkler system last checked _____________________
b) Who provided system test ____________________________
c) Water system supply source __________________________
Provide in REMARKS information on coverage for any non-required or partial automatic sprinkler system.
9.7.5, 9.7.7, 9.7.8, and NFPA 25
Observations:
Name: MAIN BUILDING - Component: 01 - Tag: 0353 Based on document review, observation and interview, it was determined the facility lacked quarterly inspections of pressurized water tank documentation, and maintain the sprinkler heads to be free of obstructions, affecting four of four smoke compartments within the component. Findings include: 1. Review of documentation on July 14, 2026, between 8:45 AM and 10:45 AM, revealed the facility lacked documentation, for quarterly, exterior suppression tank inspections. Interview at the time of the exit conference with the Administrator and Director of Maintenance on July 14, 2026, at 1:45 PM, confirmed the facility lacked documentation of fire suppression quarterly inspections. 2. Observation on July 14, 2026, between 11:45 AM and 11:50 AM, revealed sprinkler heads were subject to a load, at the following locations: a. 11:45 AM, Main Kitchen, numerous sprinkler heads; b. 11:48 AM, Main Kitchen, walk in refrigerator, 1 sprinkler head; c. 11:50 AM, Main Dining Room, exterior porch,1 sprinkler head, bird's nest. Interview at the time of the exit conference with the Administrator and Director of Maintenance on July 14, 2026, at 1:45 PM, confirmed sprinkler heads were loaded.
 Plan of Correction - To be completed: 08/14/2026

NHA educated the Director of Maintenance that the exterior suppression water tank is to be visually inspected quarterly. The Director of Maintenance completed an exterior suppression water tank inspection on 7/31/26. The exterior tank inspections will be completed quarterly and the results reported at the QAPI meeting. The numerous sprinkler heads in the Main Kitchen and walk in refrigerator and Main Dining exterior porch were cleaned to be free of obstructions. The Director of Maintenance educated the Maintenance staff that fire suppression inspection of sprinkler heads will be completed monthly on the interior and exterior sprinkler heads to ensure sprinkler heads are free of obstruction and not subject to load. Results of the monthly sprinkler head inspections will be reported at the monthly QAPI meeting for compliance.

Back to County Map


  
Home : Press Releases : Administration
Health Planning and Assessment : Office of the Secretary
Health Promotion and Disease Prevention : Quality Assurance



Copyright © 2001 Commonwealth of Pennsylvania. All Rights Reserved.
Commonwealth of PA Privacy Statement

Visit the PA Power Port