Observations Based on a plan of correction follow up inspection conducted on July 29, 2009, the facility had installed door handles on exit doors that could be locked, thus preventing egress from those marked exits.
The findings include:
A plan of correction follow up inspection was conducted on July 29, 2009 to determine if a safe environment existed for staff and clients during the ongoing construction. Marked exits from the third floor of the Fountain Springs program went through doors that had been equipped with door handles that could be locked, thus preventing egress from that exit. The doors were not locked at the time of the unannounced inspection. The locks have to be removed from those doors, or panic bars that would override the locks would have to be installed.
|
Plan of Correction On July 29, 2009, the door locks were removed from the marked exit doors on the 2nd and 3rd floors. Passage sets will be installed on marked exit doors by 8/27/09. Program Director will ensure completion. |