Observations Based on a physical plant inspection, conducted on July 27, 2022 at approximately 1:00pm, the facility failed to have pressurized hot water in the third-floor bathroom.
This finding was reviewed with facility staff during the licensing process.
|
Plan of Correction Program Director is responsible for ensuring all corrections are made in a timely manner and implemented.
Hot water valve was replaced. Defective faucet was replaced. New shut off valves were installed under vanity. Hot water was restored to third floor bathrooms on July 28, 2022.
Maintenance supervisor will check quarterly to ensure that this problem doesn't happen again. |