Observations Based upon the review of Administrative documentation, the project failed to have an annual audit of financial activities associated with the project's drug/alcohol abuse services completed upon conclusion of the fiscal year.
The findings include:
Licensing Staff conducted an Administrative Review from May 7 - 9, 2012.
Administrative documentation specified that the fiscal year runs from July 1 to June 30. However, the project's annual fiscal audit was late as it was completed February 20, 2012.
The findings were reviewed during the exit interview for the Administrative Review and were not disputed.
|
Plan of Correction At the most recent Audit Committee meeting, the necessity that all future financial audits must be completed within required timeframes was reinforced with the external independent public accountant. These timeframes were acknowledged by the independent public accountant and recorded in the meeting minutes. The Director of Finance and Accounting will maintain oversight throughout the auditing process to ensure completion in a timely manner." The Financial Audit for Fiscal Year 2011-2012 will be completed within 6 months after the June 30th close of Gaudenzia's fiscal year (by December 31st, 2012) as per Chapter 709.25(a). |