INITIAL COMMENTS |
This report is a result of an onsite follow-up inspection regarding the plans of correction for the February 16, 2012 licensure renewal inspection. The follow-up inspection was conducted on September 10, 2012 by staff from the Division of Drug and Alcohol Program Licensure. Based on the findings of the onsite follow-up inspection, Parkside Recovery was found not to be in compliance with the applicable chapters of 28 PA Code which pertain to the facility. The following deficiencies were identified during this inspection: |
Plan of Correction
|
705.22 (2) LICENSURE Building exterior and grounds.
705.22. Building exterior and grounds.
The nonresidential facility shall:
(2) Keep the grounds of the facility clean, safe, sanitary and in good repair at all times for the safety and well being of clients, employees and visitors. The exterior of the building and the building grounds or yard shall be free of hazards.
|
Observations Based on a physical plant inspection, the facility failed to keep the grounds of the facility clean, safe, sanitary and in good repair at all times for the safety and well being of clients, employees and visitors.
The findings include:
An inspection of the facility's physical plant was conducted on September 10, 2012 between approximately 8:50 AM and 9:10 AM. At the time of inspection, the grounds of the facility were not in good repair.
The walls and fixtures in the main lobby men and women's client bathrooms were covered with graffiti and needed painting.
The findings were confirmed by the facility director on September 10, 2012.
|
Plan of Correction We have painted over the graffiti which was present on September 10, 2012 We now have paint on site in order to paint over any graffiti on a daily basis. The security supervisor/facilities manager will check the bathrooms every morning and throughout the day to make sure this deficiency does not re-occur
|
705.24 (2) LICENSURE Bathrooms.
705.24. Bathrooms.
The nonresidential facility shall:
(2) Provide a sink, a wall mirror, an operable soap dispenser, and either individual paper towels or a mechanical dryer in each bathroom.
|
Observations Based on a physical plant inspection, the facility failed to provide an operable soap dispenser, and either individual paper towels or a mechanical dryer in each bathroom.
The findings include:
An inspection of the facility's physical plant was conducted on September 10, 2012 between approximately 8:50 AM and 9:10 AM. At the time of inspection, the one of the two clients ' bathrooms on the lower level in the intake area did not have soap, and either individual paper towels or a mechanical dryer. Additionally, the men ' s bathroom in the main lobby did not have soap.
The findings were confirmed by the facility director on September 10, 2012.
|
Plan of Correction Soap and paper towels were put in both bathrooms on September 10, 2012 to correct the deficiency. Every morning and throughout the day the security supervisor/facilities manager will check every bathroom to make sure there is soap and papertowels available in order to assure this deficiency does not re-occur. |