ACMH HOSPITAL Building Inspection Results For:
There are 51 surveys for this facility. Please select a date to view the survey results.
Surveys don't appear on this website until at least 41 days have elapsed since the exit date of the survey.
|
Initial Comments: Name - MAIN BUILDING Component - 01
Facility ID #270901 Component 01 Main Building
Based on an Occupancy Survey completed on March 26, 2025, it was determined there were no deficiencies as related to the requirements of the Life Safety Code for an existing hospital health care occupancy.
This Final Occupancy Survey was conducted for alterations in the basement to install a medical air compressor. The existing compressor will remain as a backup, with new intake copper pipe utilized by both compressors routed to the roof through a laundry chute no longer used for laundry. Refer to drawing number H-24-1175 (original).
This is a three-story, Type II (222), fire resistive building, with a basement and a penthouse, that is partially sprinklered.
Plan of Correction:
| |