Initial Comments: Name - MAIN BUILDING Component - 01 Facility ID #121501 Component 01 Main Building
Based on an Occupancy Survey completed on September 11, 2023, it was determined there were no deficiencies identified as related to the requirements of the Life Safety Code for an existing hospital health care occupancy.
This Final Occupancy Survey was conducted for alterations to replace an existing PET CT with a non-PET CT. Hospital will no longer have a PET CT.
Refer to Drawing Numbers: H-23-0073, H-23-0305 & H-23-0613
This is a seven-story, Type II (222), fire resistive structure, which is fully sprinklered.