Building Construction Type and Height 2012 EXISTING Building construction type and stories meets Table 19.1.6.1, unless otherwise permitted by 19.1.6.2 through 19.1.6.7 19.1.6.4, 19.1.6.5
Construction Type 1 I (442), I (332), II (222) Any number of stories non-sprinklered and sprinklered 2 II (111) One story non-sprinklered Maximum 3 stories sprinklered 3 II (000) Not allowed non-sprinklered 4 III (211) Maximum 2 stories sprinklered 5 IV (2HH) 6 V (111) 7 III (200) Not allowed non-sprinklered 8 V (000) Maximum 1 story sprinklered Sprinklered stories must be sprinklered throughout by an approved, supervised automatic system in accordance with section 9.7. (See 19.3.5) Give a brief description, in REMARKS, of the construction, the number of stories, including basements, floors on which patients are located, location of smoke or fire barriers and dates of approval. Complete sketch or attach small floor plan of the building as appropriate.
|
Observations: Name: MAIN BUILDING 01 - Component: 01 - Tag: 0161
Based on observation and interview, the facility failed to maintain building construction requirements in approximately seven locations, affecting three of three floors.
Findings include:
1. Observation on April 25, 2024, between 11:00 a.m. and 11:45 a.m., revealed steel beams, appearing to be load bearing, lacked fire proofing in the following locations: a. 11:00 a.m., One beam at angled smoke barrier doors on the ground floor; b. 11:30 a.m., One beam at angled smoke barrier doors on the second floor; c. 11:45 a.m., One beam at angled smoke barrier doors on the third floor.
This is a repeat citation from May 31, 2023.
Exit interview with the administrator and maintenance representative on April 25, 2024, at 12:30 p.m., confirmed the unprotected steel.
2. Observation on April 25, 2024, at 11:05 a.m., revealed an approximately eight-inch open hole behind a grill in the laundry room wall on the ground floor.
Exit interview with the administrator and maintenance representative on April 25, 2024, at 12:30 p.m., confirmed the wall penetration.
3. Observation on April 25, 2024, at 11:15 a.m., revealed, on the ground floor by the north hall stair, an unknown expanding foam product use to fill void penetrations.
Exit interview with the administrator and maintenance director on April 25, 2024, at 12:30 p.m., confirmed the unknown foam substance.
| | Plan of Correction - To be completed: 06/24/2024
For the first observation, the facility continues to recruit outside contractors to provide estimates for the different facets this job requires. Once approved, work will be completed. The facility has verified that no further beams within the building require fireproofing, preventing this issue from reoccurrence. For the second observation, the Maintenance Director has installed 3M Fire Barrier Self-Locking Pillows, 2"x4"x9" 90G9 ULC Listed, and sealed with Metacaulk FRP fire rated putty, 12Y3 UL Listed in order to maintain the fire barrier's fire rating. Facility will ensure that through-wall penetrations exposed during future building changes will be properly repaired to fire rating standards. For the third observation, the Maintenance Director will remove all firestop foam from the penetration and seal it with 3M Fire Barrier Sealant FD-150+, 90G9 UL Listed. Additionally, the facility will ensure that through-wall penetrations made during future building changes will be properly sealed to fire rating standards.
Facility will be requesting an extension/waiver as we are uncertain as a confirmed date contractors will be out to complete project.
|
|