Corridor - Doors Doors protecting corridor openings in other than required enclosures of vertical openings, exits, or hazardous areas resist the passage of smoke and are made of 1 3/4 inch solid-bonded core wood or other material capable of resisting fire for at least 20 minutes. Doors in fully sprinklered smoke compartments are only required to resist the passage of smoke. Corridor doors and doors to rooms containing flammable or combustible materials have positive latching hardware. Roller latches are prohibited by CMS regulation. These requirements do not apply to auxiliary spaces that do not contain flammable or combustible material. Clearance between bottom of door and floor covering is not exceeding 1 inch. Powered doors complying with 7.2.1.9 are permissible if provided with a device capable of keeping the door closed when a force of 5 lbf is applied. There is no impediment to the closing of the doors. Hold open devices that release when the door is pushed or pulled are permitted. Nonrated protective plates of unlimited height are permitted. Dutch doors meeting 19.3.6.3.6 are permitted. Door frames shall be labeled and made of steel or other materials in compliance with 8.3, unless the smoke compartment is sprinklered. Fixed fire window assemblies are allowed per 8.3. In sprinklered compartments there are no restrictions in area or fire resistance of glass or frames in window assemblies.
19.3.6.3, 42 CFR Parts 403, 418, 460, 482, 483, and 485 Show in REMARKS details of doors such as fire protection ratings, automatics closing devices, etc.
|
Observations: Name: MAIN BUILDING 01 - Component: 01 - Tag: 0363
Based on observation and interview, it was determined the facility failed to maintain four corridor openings, affecting three of three floors.
Findings include:
Observation on August 20, 2025, between 11:22 a.m., and 12:04 p.m., revealed the following:a. 11:22 a.m., holes within the first floor, Rosewood Clean Linen Room door.
b. 11:43 a.m., the second floor Pantry door required adjustment to fully latch.
c. 11:52 a.m., the basement-level, Dry Storage Room door required adjustment to fully latch.
d. 12:04 p.m., the basement-level, Staff Lounge door required adjustment to fully latch.
Exit interview on August 20, 2025, between 12:45 p.m., and 1:00 p.m., with the Executive Director, the Administrator, and the Facilities Manager, confirmed the corridor opening deficiencies.
| | Plan of Correction - To be completed: 09/30/2025
a. The hole in the Rosewood Clean Linen door will be filled with a fire rated caulk. Completion by 9/26/2025.
b. The 2nd floor pantry door will be adjusted to properly latch. Completion by 9/26/2025.
c. Dry Storage room door closer will be replaced to provide positive latching. Completed by 9/26/2025.
d. The door to the staff lounge will be adjusted to positively latch. Completed by 9/26/2025.
|
|