QA Investigation Results

Pennsylvania Department of Health
GEISINGER-LEWISTOWN HOSPITAL
Building Inspection Results

GEISINGER-LEWISTOWN HOSPITAL
Building Inspection Results For:


There are  66 surveys for this facility. Please select a date to view the survey results.

Surveys don't appear on this website until at least 41 days have elapsed since the exit date of the survey.



Initial Comments:
Name - MAIN BUILDING Component - 01
Facility ID #121501
Component 01
Main Building

Based on an Occupancy Survey completed on September 11, 2023, it was determined there were no deficiencies identified as related to the requirements of the Life Safety Code for an existing hospital health care occupancy.

This Final Occupancy Survey was conducted for alterations to replace an existing PET CT with a non-PET CT. Hospital will no longer have a PET CT.

Refer to Drawing Numbers: H-23-0073, H-23-0305 & H-23-0613

This is a seven-story, Type II (222), fire resistive structure, which is fully sprinklered.


Plan of Correction: